SCCM DP migration from Primary site to new server
Question
Hi All,
I have one primary site and DP is installed on the same primary site last week client asked to move DP from primary site to a new brand 2016 server.
What are the prerequisite for new DP setup?
How can we move all deployed packages from existing DP (Which is on primary) to new setup DP?
when we should remove DP role from primary site completely?
Please share if any Docs, Link i need to prepare a plan so please help.
Answers ( 3 )
Try https://www.anoopcnair.com/sccm-install-new-distribution-point-role/
It’s better to distribute packages to new DP… to make it a clean move
Once all clients started using new dp … you can remove the old DP
Sir, i have around 1500 PKG’s already distributed on existing DP (Primary server) do we need to redistribute them on New DP?
That is the best way … I would suggest … to have a clean DP