I made a task sequence Required (Available immediately but scheduled after 5 days) to several machines, but before the scheduled date I deleted it (for a specific reason).
Then I created a new TS for the same machines. Will this create a problem with policies for the machines? If some machines already received policy for earlier TS (since I made deployment Available immediately), will that earlier policy be erased and will the machines automatically receive policy for the new TS? Do I need to do anything specifically in regards to com objects /policy cleanup first?
Thank you!
Answers ( 2 )
Normally the client is intelligent to get updates on the next policy sync schedule … no need to do anything specific (I think)